Contract number :
1142/2009314
Project start date :
April 2009
Running time :
22 months
Employer :
Arfa Steel and Iron Company
Employer address :
Gol Gohar Building, Fatemi St., Tehran
Employer :
Arfa Steel and Iron Company
Consulting engineer :
Steel Technical Engineering Company
Project information
Implementation of a steel plant with a nominal capacity of 8,800 tons per year, including:
Soil operation: 403,167 cubic meters, concreting: 70.000 cubic meters, buildings: 70.000 square meters, electricity and precision instruments: up to 3,000 tons, installation of steel structure: 17.000 tons, installation of equipment:13.000 tons, piping: 400.000 inches in diameter