Contract number :
-
Project start date :
July 2011
Running time :
29 months
Employer :
Oil Industry Engineering and Construction Company (OIEC)
Employer address :
No. 2, Pirooz Alley, South Kamraniyeh, Tehran
Employer :
Oil Industry Engineering and Construction Company (OIEC)
Consulting engineer :
EIED Company

Project information
Installation and pre-commissioning of all refinery facilities and Main Pipe rack including:
Ground operations: 244,000 cubic meters
Concreting: 47,000 cubic meters
Installation of steel structure: 11,000 tons
Equipment installation: 3772 tons
Plumbing and insulation: 702,000 inches in diameter
Power and precision instruments: 2000 tons + 1000 km of cabling
Coloring: 169,000 square meters