Contract number :
19751
Project start date :
January 2007
Running time :
30 months
Employer :
National Iranian Steel Company
Employer address :
Valiasr St., Tehran,
Employer :
National Iranian Steel Company
Consulting engineer :
Tara Design Company
Project information
Implementation of units for unloading and transfer of materials and direct reduction to a capacity of 000,800 tons per year, including:
Soil operation: 226000 cubic meters, concreting: 36.000 cubic meters, preparation and installation of steel structure: 5.000 tons, installation of equipment: 320.12 tons, piping: 120.000 inches in diameter
Electricity and instrumentation: 431 km